Analysis of formwork unit

 Analysis of formwork unit price based on national standards Indonesia (SNI)


*Install 1 m2 formwork for the foundation

Material price analysis

Wood Class III 0.040 m3

Nails 5 cm - 10 cm 0.300 kg

Oil formwork 0.100 Liter

Labor cost analysis

Workers' OH 0.520

0.260 carpenter OH

0.026 handyman labor chief OH

0.026 foreman OH


*Install 1 m2 formwork for sloof

Needs Unit Index

Material price analysis

Wood Class III 0.045 m3

Nails 5 cm - 10 cm 0.300 kg

Oil formwork 0.100 Liter

Labor cost analysis

Workers' OH 0.520

0.260 carpenter OH

0.026 handyman labor chief OH

0.026 foreman OH


*Install 1 m2 formwork for column

Material price analysis

Wood Class III 0.040 m3

source : http://networkedblogs.com/cW7U5