*Install 1 m2 formwork for the foundation
Material price analysis
Wood Class III 0.040 m3
Nails 5 cm - 10 cm 0.300 kg
Oil formwork 0.100 Liter
Labor cost analysis
Workers' OH 0.520
0.260 carpenter OH
0.026 handyman labor chief OH
0.026 foreman OH
*Install 1 m2 formwork for sloof
Needs Unit Index
Material price analysis
Wood Class III 0.045 m3
Nails 5 cm - 10 cm 0.300 kg
Oil formwork 0.100 Liter
Labor cost analysis
Workers' OH 0.520
0.260 carpenter OH
0.026 handyman labor chief OH
0.026 foreman OH
*Install 1 m2 formwork for column
Material price analysis
Wood Class III 0.040 m3